Skip to main content

Operation and Maintenance Services of the pipeline from Torre de Abraham Dam to Gasset Reservoir for water supply of Ciudad Real and the close region, Part I (Spain)

ACUASUR - South of Spain Water Authority

Gasset

PURPOSE OF THE WORK
In the contract there are defined several works related to the Operation, Maintenance and Upkeep of the pipeline of water supply that connect Torre de Abraham and Gasset Reservoirs, managed by Aguas de las Cuencas del Sur (AcuaSur). This pipeline of ductil iron with nominal diameter of DN 1000 mm is 29 km long and has an emergency pump station and a special discharge valve at the end of the conduction.
The pipeline system starts working when is receiving an order of 45 mwp. Along the conduction there are 3 remote control units which are connected to the Control Center of ACUASUR located in Ciudad Real by GPRS, being provided each one with two power generators, solar panels and storage battery, so no external electric power is needed.
The power supply system consists of cover energy only with the generator in such a way there will be an independent service that will not exist if the batteries are used.

gasset

The work to be carried out includes:

  • Preliminary activities of analyses of the situation.
  • Stock list of equipment and items.
  • Updating and development of Preventive Maintenance Program (PMP).
  • Maintenance and Upkeep of different elements or items of pipeline.
  • Inspection of civil works and mechanical and hydraulic equipment.
  • Operation works of the pipeline.
  • Preparation of the Annual Report of operation and maintenance.
  • Preparation of reports and projects.